Welcome to PACE
Infrastructure Delivery Professionals. Battle-tested in rail's toughest programmes. Now powered by Aikido's intelligence.
PACE deliver project and programme management for Britain's most complex rail and infrastructure schemes — enhanced by the Aikido Intelligent Control Platform for real-time visibility, automated reporting, and multi-stakeholder assurance.
Why Choose PACE as your Project partner
Expert teams driving confident proven project delivery
Proven Rail Expertise
25+ years delivering complex rail and infrastructure programmes with confidence and precision.
Intelligent Programme Control
Aikido provides real-time visibility, reporting and governance across programmes.
Delivery Focused
Practical expertise focused on better outcomes for complex programmes.
ABOUT AIKIDO
Centralised, accessible integrated Project Management, controls and reporting.
One platform, one source of truth. A truly integrated system reading from source data and core applications bringing all the data into a common data environment, providing assurance and insights
Aikido brings large volumes of fragmented programme data into one visually engaging and clear view — so rail and infrastructure teams can stop chasing spreadsheets and start delivering with confidence.
AI-powered analysis surfaces risks, runs predictive analysis, highlights unacceptable variances, and helps your teams focus where it counts.


WHAT WE DO
Expertise That Moves Complex Programmes Forward

CASE STUDIES
Proven Delivery. Real-World Results.
From Concept to Rail Awards at the UK's busiest Station
A scheme that had become unaffordable due to the escalating scheme cost, was in delay, did not have a compliant engineering solution and had lost stakeholder confidence.
Reimagining the delivery methodology and delivering the reality of a seamless major infrastructure project implementation. Also our first deployment of Aikido
Key results:
33 months programme reduction
Significant cost savings
No negative station or operations impact
Aikido created significant project saving and delivery efficiencies.
Norwich, Yarmouth & Lowestoft Electrologix re-signalling.
Electrologix was the new signalling interlocking with its first major 38-mile installation on the NYL route, part of the full system upgrade with a full rolling stock replacement. The scheme had gone into delay and had escalating cost. Greater Anglia had lost confidence and the railway access strategy could not be agreed.
Key results:
Delivery to plan of a re-baselined programme
Long term access strategy plan agreed with significant reduction in required access.
Controlling mind and delivery of route wide 21-day blockade day blockade
Gospel Oak to Barking electrification - Scheme recovery to full Authorisation
One of the most politically pressured Network Rail electrification schemes had gone into significant delay. The Transport for London Overground trains were being delivered and had to go into service to meet the new UK timetable
Key results:
Full programme stabilisation
Delivered to the agreed recovery plan, electrifying the infrastructure within 12 month
One of the first major electrification schemes to go through the full CSM Authorisation process
CONTACT
Ready to Take Control of Your Programme?
Contact
+44 (0)7876 202004